The table below is intended to give you an estimate of how long people have waited on the housing register before being allocated a property.

These figures are taken from a 12 month period from 4 January 2025 - 4 January 2026.

Type / size No. of lets Shortest wait Longest wait Average wait
1 beds* 104 3 weeks 747 weeks 64 weeks
2 beds* 79 3 weeks 242 weeks 80 weeks
3 beds 27 9 weeks 667 weeks 126 weeks
4 beds 3 42 weeks 225 weeks 104 weeks
5 beds 0 - - -

*includes a large number of sheltered properties for 50+ age group

How many people are on the waiting list?

The total number of active households on the Council’s housing waiting list as of 3 December 2025 is 1262.

The below table provides a snapshot of the number of people that are currently in each band with their calculated bedroom need.

Band 1 bed* 2 bed* 3 bed 4 bed 5 bed+ Total per band
A 10 3 2 0 1 16
B 83 34 73 18 3 211
C 192 160 95 22 7 476
D 8 1 0 0 0 9
E** 316 145 61 10 0 532
Total per bed needed 609 343 231 50 11 1244

*includes a large number of applicants (50+ age group) eligible for sheltered accommodation.

**includes people who are adequately housed, with no local connection, or who exceed the financial thresholds.