Phase 1 - currently underway
This first phase is anticipated to run from the start of the works on 7 April 2025 to the end of May 2025.
- A compound will be set up within Foresters Way car park and initial enabling works will start.
- Foresters way will be closed off to vehicle traffic and there will be realignment and construction of the new carriageway/footway provision along Foresters Way/Shellons Street.
- The bus stop adjacent to the Foresters Way car park will be temporarily suspended during this period.