Project progress

Phase 1 - currently underway

View along Shellons Street from Grace Hill roundabout

This first phase is anticipated to run from the start of the works on 7 April 2025 to the end of May 2025.

  • A compound will be set up within Foresters Way car park and initial enabling works will start.
  • Foresters way will be closed off to vehicle traffic and there will be realignment and construction of the new carriageway/footway provision along Foresters Way/Shellons Street.
  • The bus stop adjacent to the Foresters Way car park will be temporarily suspended during this period.