Phase 3 - currently underway


This phase will start in July/August 2025 and run into early 2026.
-
Work will take place along Cheriton Road between Shorncliffe Road and Middelburg Square and also at Shorncliffe Road junction. This will include utility diversions and construction of rain gardens and footways.
- Work around Middelburg Square will continue to tie in to works being completed along Cheriton Road.
- Paving and tree works along Guildhall Street will start during this phase.

- Phase 1A - Cheriton Road (middle) - New Drainage Works (PDF, 679KB) - COMPLETE
- Phase 1B - Shorncliffe Jnc – New Drainage Works (PDF, 667KB) - IN PROGRESS
- Phase 2C - Cheriton Road (middle) - New Footway Works (PDF, 304KB) - COMPLETE
- Phase 4A - Middleburg Square West - New Drainage and Road, PDF, 553KB) - COMPLETE
- Phase 4B - Middleburg Square West - New Drainage and Road, PDF, 604KB) - COMPLETE