Project progress

Phase 2

View of Sandgate RoadView of The Folca building on Sandgate Road

This will run for several months from May 2025 and is likely to overlap with phase three given the interconnectivity of the scheme.

Improvements will be made around Middelburg Square including the infilling of the two subways at the junctions with Cheriton Road and Cheriton Gardens

  • A new signalised traffic junction will be created at the Middelburg Square/Cheriton Gardens junction
  • Work will take place along the southern end of Middelburg Square including the construction of a new footway
  • Preparations will begin for the new linear bus stop arrangement along Middelburg Square. This is currently scheduled for mid-July/early August. All bus stop works on Middelburg Square will be completed before the existing bus station in Bouverie Square is closed.
  • Changes to the Radnor Park roundabout will also begin during this phase, including the installation of the new cycle lane and construction of the junction with Station Approach.
  • Tree planting and paving works will also take place along Sandgate Road

Please see the traffic management plans for this phase of work below: